The new emergency response storage facility with an integrated rescue station in Ochtrup is being waterproofed with Geficon® UDB bonded waterproofing membrane across a total area of approximately 3,500 m². The project is being carried out on behalf of the District of Steinfurt.
The waterproofing in the rescue station area was completed in 2025. More recently, the first section of the emergency response storage facility, together with additional adjoining areas, has been installed. The current construction progress can be seen in the images, where the completed areas are highlighted in green. The significantly larger construction phase will begin shortly.